june 2018

In June, 50% of all exterior siding and trim was completed. The rough mechanical systems are being finalized in preparation for drywall. 

may 2018

In May, the Davis353 construction team began exterior finishes. All mechanical, electrical and plumbing work was started in preparation for drywall.

April 2018

In April at  Davis353, the roof and windows were installed. Your new home is taking form!

March 2018

In March, all interior framing was completed.

FEbruary 2018

February was a busy month for Davis353 construction! Wood framing for all floors was completed as well as the interior layout of the units. Utilities were tied in and underground work for plumbing was finished.

JANUARY 2018

The Davis353 Drone shows the worksite as the workers for The Maggiore Companies poured the foundation to get it completed before the winter. The video really shows that this modern complex is truly nestled in an amazing neighborhood, steps away from the action of Davis Square.